Rush Wall Wind Turbine

Project Name
Rush Wall Wind Turbine
Project Location
Magor near Newport, Wales
Client
Clean Earth Energy Ltd
Client’s Project Manager
Quad Consulting
Turbines
1no Vensys 136
Height to tip 150m
Max Power Output 3.5MW
Key Info
-
150m tip height turbine in difficult ground conditions
-
81no CFA piles
-
1500m3 of concrete in foundation
-
Cost saving introduced by use of cofferdam
-
Private wire project through power purchase agreement
Description
As specialists in the construction of onshore wind turbines, Green Cat Contracting were appointed to act as Principal Contractor and provide the access and foundation works for a Vensys 136 3.5MW turbine, measuring 150m to blade tip. The ground conditions on site were poor, especially for a turbine of this size, consisting of a thick lens of peat overlying soft clays, before eventually encountering completely weathered stiff clays of the Mercia Mudstone group at >10m depth.
A piling mat was first constructed over the weak insitu soils and 81no CFA piles were installed, socketing into the competent strata. To provide a cost saving to the client, Green Cat Contracting employed a cofferdam arrangement to facilitate the excavation of overburden and the subsequently required Class 6A replacement into the peat layer. This prevented the requirement for extensive over-excavation to facilitate access and subsequent replacement with imported fill.
After the foundation earthworks and improvements were complete, a 750mm thick raft slab was installed, followed by a 20m octagonal foundation totalling circa 1000m3, with over 250 tonnes of rebar required to complete the base.
More onshore wind projects
Hendy Wind Farm
Green Cat Contracting were employed as Principal Contractor on a design and build basis to provide 7no Vestas V80 turbines plus associated roads, d...
Rush Wall Wind Turbine
As specialists in the construction of onshore wind turbines, Green Cat Contracting were appointed to act as Principal Contractor and provide the ac...
Binn EcoPark Wind Farm
Green Cat Contracting were appointed as Principal Contractor to deliver the BoP works for 4no Enercon E92 turbines at the Binn EcoPark near Glenfar...
Deuchries Wind Farm
Green Cat Contracting were appointed as Principal Contractor to deliver the BoP works for 3no Enercon E82 turbines near Aberchirder, Aberdeenshire ...
Hoprigshiels Wind Cluster
Green Cat Contracting were appointed as Principal Contractor to deliver the BoP works for 3no Nordex N90 turbines on a design and build basis, incl...
Welton of Creuchies
Green Cat Contracting were appointed as Principal Contractor to deliver the BoP works for 4no Enercon E82 turbines on a design and build basis, inc...
Pogbie Wind Farm
Green Cat Contracting were appointed as Principal Contractor to deliver the BoP works for 12no Enercon E53 turbines on a design and build basis, in...